Cafe electrical design: kitchen, hall, ventilation and panel

A cafe electrical project covers three load centres at once — a kitchen with peak thermal loads, a dining hall with sockets and lighting, and ventilation that must run with the kitchen. This guide shows the group layout, the panel arrangement and the document set for approval.

Author:GorkyCAD Team

Cafe zones: kitchen, hall, bar, ventilation

A cafe splits naturally into four electrical zones, each with its own load character. The kitchen holds thermal equipment, dishwashers and refrigeration with long duty cycles. The hall needs general and decorative lighting plus cleaning sockets. The bar combines coffee machines, grinders and display refrigeration on a small footprint. Ventilation — supply, exhaust and the kitchen hood — ties the zones together, because the hood must start with the cooking line.

Draw zone boundaries on the plan first and list every consumer with its rated power. This table becomes the basis for groups, cable sizing and the panel schedule, and it is also what the landlord asks for when allocating capacity.

  • Kitchen: ovens, fryers, dishwasher, fridges, small appliances.
  • Hall: lighting scenes, cleaning sockets, music and display equipment.
  • Bar: coffee machine, grinders, showcase fridges, cash desk.
  • Ventilation and air conditioning: hood, supply/exhaust fans, split systems.

Kitchen peak loads and incomer margin

The kitchen defines the incomer: thermal appliances switch on together during service and stay on for hours. Sum the rated powers, apply demand and simultaneity factors, and check the resulting design current against the capacity the landlord allocated. A 20–30% margin for a second oven or an extra fridge is standard practice, not luxury — cafes change menus and equipment often.

Size the incomer cable and main breaker for the diversified peak, then verify voltage drop within the 5% total limit and short-circuit disconnection at the farthest kitchen socket. Calculations are preliminary until an engineer signs them, but getting the margin right at this stage prevents a costly incomer upgrade later.

Groups and panel: what goes dedicated

Kitchen equipment sits on dedicated groups: oven, fryer, combi oven, dishwasher and each coffee machine get their own breaker sized to the appliance rating. Refrigeration goes on separate groups too, so a tripped fryer breaker never takes out the fridges overnight. Ventilation and the hood form their own group interlocked with the cooking line where local rules require it.

The hall and bar are grouped by function: lighting scenes, cleaning sockets, bar equipment and outdoor signage each get a group. In the panel this gives a readable structure — incomer, kitchen block, hall block, bar block, ventilation — which the auto-assembled panel schedule in GorkyCAD builds from the same model as the plan, with phase balancing across the three phases.

Metering, hall sockets and lighting

Metering starts the project, not ends it: record where the settlement meter stands, whether the cafe needs its own sub-meter inside a food court, and how readings are taken. Agree these points with the landlord before fit-out, because moving a meter cabinet later costs more than the whole lighting budget.

Hall sockets are planned for cleaning and events rather than guests: one double socket per 8–10 metres of perimeter plus points for the cash desk, music and window displays. Lighting runs in two or three scenes — general, accent and emergency — so staff can dim the hall without touching kitchen or escape lighting. USB charging points at tables are a fit-out decision worth fixing on the plan early.

Document set for approval

A landlord or food-court operator typically expects a compact set: the equipment layout plan with groups, the single-line diagram generated from the model, the panel schedule with breaker ratings and cable sizes, the cable schedule, and the estimate with the price date. GorkyCAD exports this as one PDF set — plan, single-line, panel schedule, specification, cable schedule and estimate — so the approval pack and the installer's pack never diverge.

Attach the capacity allocation letter and the metering arrangement description. If the fit-out changes equipment mid-way, reissue the single-line and the schedule with a new revision number instead of patching PDFs by hand — the model regenerates the documents consistently.

Common mistakes in cafe projects

The classic error is hanging thermal appliances on shared socket groups to save breakers — the group trips at Friday-evening peak and takes the display fridge with it. The second is forgetting the hood interlock and the grease-filter lighting circuit. The third is no spare ways in the panel: a cafe without two or three spare modules buys a new panel with its first menu change.

Run the built-in checks before issue: 25 checks against IEC 60364 on the international pricing tier catch missing RCD protection, overloaded groups and voltage-drop exceedances. They assist the review but never replace it — the engineer of record approves the design.

Build it in GorkyCAD: one model, full set

Draw the cafe plan in the browser editor, place equipment with rated powers, and let the single-line diagram generate itself from the model instead of being redrawn by hand. The panel assembles automatically with phase balancing, and the estimate with 14-day price freshness shows materials, labour and VAT. See the full terms on the pricing page — Pro is €40/mo with 20,000 AI tokens included.

Start free in the editor, check the project against 25 IEC 60364 rules, then export the PDF set for the landlord. Calculations and AI suggestions stay preliminary until the responsible engineer approves them.

FAQ

What supply size does a small cafe need?

There is no universal figure: a small coffee point with a display case may fit into 15–25 kW, while a full kitchen with electric stoves, ovens and dishwashers often needs 50–100 kW or more. Start from the equipment list with rated powers, apply demand factors, and agree the available capacity with the landlord and the grid operator before drawing groups. Any calculation below is preliminary until an engineer approves it.

Do cooking appliances need dedicated groups?

As a rule, yes. Ovens, fryers, combi ovens and dishwashers are high continuous loads with heating elements, so each gets a dedicated group sized for its rated current, with its own breaker and, where required, RCD protection. Sharing one group between two thermal appliances leads to nuisance tripping and overheated cable — separate groups also make fault-finding and maintenance simpler.

Is expert review required?

It depends on the jurisdiction and the premises: a fit-out inside a shopping centre usually passes the landlord's technical review rather than a state expert review, while a standalone building or a capacity increase may require formal approvals and utility sign-off. Clarify the route early — the document set is the same, but the approval stamp differs.

What should be handed to the landlord?

Hand over the as-fitted plan, the single-line diagram, the panel schedule with breaker ratings, the cable schedule and the estimate with the price date. Record the allocated capacity, the metering point boundaries and who pays for alterations. Photos of hidden routes before ceilings close save disputes later.