Procedure
Application to the network owner → technical conditions (TC) → contract → execution → connection and meter sealing. In RF, 550 ₽ for up to 15 kW (standard procedure).
Technical conditions
TC specify: allocated power, connection point, metering requirements, protection. The project is made per the TC.
Documents from the owner
Passport, ownership documents, plan of the land plot. The network organization prepares the contract.
What the electrician does
Prepares the project per the TC, coordinates the input (pole/box), selects the metering panel, supervises the connection.
Timelines
Standard connection — up to 6 months from the contract; 1 year for complex cases (5th category).
How GorkyCAD helps
The input panel with metering per the TC is designed in GorkyCAD — SLD, panel and passport are ready for the network organization.
Frequently asked questions
Yes, all articles and calculators are completely free.
The site offers 21 free calculators: cable sizing, breakers, RCD, voltage drop and more.
In GorkyCAD Pro: plans, panels, calculations and a PDF set for free.
Write to hello@gorkycad.pro — specialists will review and correct it.