Three blocks: materials, labour, VAT
Every estimate you will ever sign follows the same skeleton. Materials are everything that stays on site: cable, breakers, RCDs, enclosures, sockets, switches, luminaires, trays and fasteners. Labour is everything the crew does: chasing, pulling cable, terminating, assembling panels, testing and commissioning. Taxes — VAT where applicable — sit on top as their own block, calculated from the subtotal rather than dissolved into it.
Overheads and contingency are legitimate too, but only as separate lines with names, not as silent padding inside positions. The moment you see this four-part structure — materials, labour, taxes, allowances — you are reading the document correctly. Everything below is detail: how to check each block line by line.
Materials: items and quantities
The materials section is checked against the design, not against gut feeling. Each line should carry a name, a unit, a quantity and a unit price: metres of each cable type, number of breakers by rating, enclosures, metres of trunking. Quantities that match the specification and the cable schedule are a good sign; round numbers everywhere ('100 m', '50 pcs') with no link to drawings are a warning sign.
Two further checks separate careful contractors from the rest. First, the price-book date: material prices move, so an estimate without a stamped price date cannot be compared or honoured months later. Second, named versus equivalent items: 'or equivalent' is acceptable only when the substitution criteria are written down. Anything else turns acceptance into an argument about what was actually installed.
Reconcile materials against the project specification line by line: every estimate position should exist in the specification and vice versa. Pay special attention to cables — type, cores, cross-section and metres come from the cable schedule. Swapping the cable type at the same cross-section is a favourite way to cheapen an estimate while losing quality, and the schedule exposes it immediately.
Labour: points, metres, panels
Labour pricing in electrical work is traditionally tied to measurable units: wiring points, metres of chase or cable run, panels assembled, luminaires hung. This is convenient for comparison — but only when both estimates count the same scope. Ask what a 'point' includes in this particular document: just pulling the cable, or chase, box, termination and testing as well.
Panels deserve their own lines: assembly, labelling, balancing across phases and testing are real work, not a footnote to material cost. The same goes for commissioning — insulation tests, loop checks, RCD tests and a trial run. If commissioning is missing from the labour section entirely, you will pay for it later as 'additional works', which is the most expensive way to buy it.
Pin down the contents of a 'point' in writing: chasing, box, cable up to an agreed length, termination and testing, for example. Without that definition, comparing two estimates is guesswork — one contractor's point includes everything, another's covers only the cable pull, and the rest resurfaces as extras. The same precision is needed for panels: way counts, circuit labelling, testing.
Overheads and contingency: the honest norm
Transport, scaffolding, waste removal, site management — real costs that belong in the estimate as named lines. Contingency covers what nobody can see inside walls and floors until work starts. There is no universal percentage for it: an old building with no survey deserves more reserve than a new flat with a finished design. The figure is negotiated and written down.
The rule is visibility. A contingency shown as its own line can be discussed, reduced or released at the end; a contingency smeared across material prices can only be paid. The same applies to 'unforeseen works' clauses: they should describe a procedure (survey, approval, rate card), not serve as a blank cheque. An estimate that hides its reserves inside positions is telling you something about its author.
Checking the estimate against the design
The strongest check needs no pricing knowledge at all: every material line should trace back to the drawings. Cable metres to the cable schedule, breaker counts to the panel schedule, luminaire counts to the lighting layout, chasing metres to the floor plan. In a model-based workflow this reconciliation is almost free, because the specification and the estimate come from the same engineering model as the drawings — quantities cannot silently drift between documents.
Work the other direction too: every element on the drawings should appear in the estimate. A panel on the single-line diagram with no assembly line in labour, or twenty downlights on the plan with none in materials, means the totals are fiction regardless of how precise they look. Estimates are advisory documents until signed; the signature belongs to whoever takes responsibility for the numbers.
A strong move is to ask the contractor for the documentation set itself: layout, single-line diagram, panel schedule and cable schedule. A 'estimate versus drawings' reconciliation takes an evening and exposes nearly every padding trick — extra metres, missing breakers, forgotten works. A contractor with nothing to hide hands the set over calmly.
Formatting: PDF sheet plus XLSX, price date stamped
| Section | What to check | Red flag |
|---|---|---|
| Materials | Items, quantities, units, price date | Round numbers with no link to drawings |
| Labour | Points, metres, panels, commissioning | 'Point' undefined; no testing lines |
| Taxes | VAT as a separate block | Tax dissolved into positions |
| Allowances | Named lines with a procedure | Reserves hidden inside prices |
Ask for the estimate in two forms: a signed PDF sheet for the record and an editable XLSX for verification — XLSX export is part of the Pro tier. Either way, demand the price-book date on the face of the document and agree in writing how long prices are held. Tariffs are on the pricing page: start free in the editor, and move to Pro (€40/mo) when the project needs full documentation and exports.
The finished PDF set follows one model: layout, single-line diagram, panel schedule, specification, cable schedule and estimate as a single package, so figures cannot drift between files. Keep this set with the estimate until the warranty ends — in disputes over extras it becomes the main document, not messenger chat history.
FAQ
What must an estimate include?
At minimum: a line-by-line list of materials with quantities and units, a labour section tied to measurable scope (points, metres, panels), taxes shown separately, the price-book date, and totals that arithmetically follow from the lines. Anything missing from this list is a reason to ask questions.
What is a normal contingency?
There is no universal percentage: it depends on the age of the survey, the state of the walls and the completeness of the design. What matters is that contingency is a separate, visible line — not quietly dissolved into material prices or labour rates.
Why does labour cost more than materials?
Often yes: chasing, pulling, terminating, panel assembly and commissioning are manual work, while copper and devices reprice in jumps. The suspicious picture is the reverse — cheap labour against expensive materials usually means part of the work will resurface later as chargeable extras.
How do I check the estimate against the drawings?
Trace every material line back to the drawings: cable metres to the cable schedule, breaker counts to the panel schedule, luminaires to the layout. Then work backwards: every element on the drawings must appear in the estimate. A panel with no assembly line, or downlights with no material positions, means the totals are fiction.
Related articles
- Electrical estimate checklist: 12 checkpoints
- Electrical material list: what not to forget
- How much electrical installation costs
- Electrical takeoff: counting points and metres
Build an honest estimate in GorkyCAD
Build the estimate from the same model as the drawings: materials, labour and VAT in one PDF set and XLSX, with the price date stamped.
Open GorkyCAD