Why the general inspection is not enough

A standard home inspection covers hundreds of items in a few hours, and electrical usually gets a quick pass: a few receptacles tested, the panel photographed, done. That pass misses the expensive problems — undersized services, obsolete panels, bootleg grounds, buried junction boxes — because finding them requires opening covers, reading labels, and doing load math.

The stakes are financial as well as physical. A panel replacement runs $1,500 to $3,000, a service upgrade $2,500 to $5,000, and a full rewire of a 2,000 sq ft house $8,000 to $20,000 depending on region and access (market estimates, not quotes). Discovering these before closing lets you renegotiate, demand repairs, or walk away. After closing, they are yours.

Order a dedicated electrical inspection when the house is older than about 25 years, the panel brand is unfamiliar, the seller discloses DIY electrical work, or you plan to add an EV charger, heat pump, or workshop — all of which demand service capacity the house may not have. Check what a charger needs in our EV charger circuit sizing guide.

Panel brand and type: the five-minute disqualifier

Open the panel door (or have the electrician do it) and read the brand on the label. Certain legacy panels have documented breaker failure rates and cause insurance problems: Federal Pacific Stab-Lok, Zinsco / Sylvania-Zinsco, and Challenger panels with specific breaker lines are routinely flagged by insurers, and some carriers decline coverage until they are replaced. Pushmatic panels are less alarming but obsolete, with stiff mechanisms and scarce parts.

Also check the panel anatomy: main breaker present and labeled, no double-tapped breakers (two wires under one lug not listed for it), no mismatched breaker brands jammed onto the bus, and every slot either filled or properly blanked. Rust, moisture staining, or a burnt smell inside the enclosure means water entry or past arcing — investigate before anything else.

A fuse box is not automatically a fail — fuses protect fine — but most insurers surcharge them, 60 A fuse services cannot support modern loads, and tampering (pennies behind fuses, oversized fuses on small wire) is common. Budget a panel replacement in your offer math whenever you see one.

Service size: is 100 A enough for you?

Service size is the ceiling on everything the house can run at once. Legacy houses carry 60 A; most post-1980 houses have 100 A; large or all-electric homes need 200 A. The question is never the number alone — it is the number against your loads: EV charger (40–60 A), heat pump or AC (20–40 A), electric range (40–50 A), dryer (30 A), water heater (25–30 A).

Run a quick standard-method sanity check per NEC 220.82: take the general lighting and receptacle load at 3 VA per sq ft for a 2,000 sq ft house (6,000 VA), add small-appliance and laundry circuits (1,500 VA each, minimum two plus one), apply the 40 percent demand to the amount above 10,000 VA, then add major appliances at nameplate. A 2,000 sq ft all-electric house with range, dryer, and water heater typically lands near 24,000–28,000 VA (100–120 A at 240 V) — a 100 A service is already marginal before any EV charger.

If the service is 60 or 100 A and you plan electrification, price a 200 A upgrade into the offer. Our comparison of 100 A vs 200 A service upgrades walks through the full cost breakdown.

Household profileEstimated demandRecommended service
Gas heat and cooking, no EV60–80 A100 A adequate
Gas heat plus one EV charger100–130 A200 A upgrade
All-electric, no EV100–130 A200 A recommended
All-electric plus EV and heat pump140–180 A200 A minimum; 320/400 A for very large homes

Grounding and bonding: the invisible safety net

Grounding gives fault current a low-impedance path home so the breaker trips fast; bonding connects all metal parts so they rise and fall together. Verify: a grounding electrode conductor leaving the panel, a water-pipe bond where metal piping exists (jumpers across the meter), and exactly one neutral-to-ground bond at the service — never in subpanels (NEC 250.24(A)(5) and 250.142).

Red flags: no visible ground rod or Ufer connection, cut or disconnected bonding jumpers (common after plumbing remodels swap copper for PEX), subpanel neutrals and grounds mixed on one bar, and three-prong receptacles that test open-ground. A $15 tester cannot distinguish a real ground from a bootleg jumper between neutral and ground at the receptacle — the latter hides an open ground and energizes the chassis path. That distinction takes a meter and a panel look.

Old two-wire houses without equipment grounding are manageable: NEC 406.4(D) permits GFCI protection with “No Equipment Ground” labels as a retrofit. Missing grounding plus no GFCI anywhere is the combination to fear. Background reading: grounding vs bonding explained.

GFCI and AFCI protection where it belongs

Current code requires GFCI protection in kitchens, bathrooms, garages, outdoors, crawl spaces, basements, laundry areas, and within 6 feet of sinks (NEC 210.8(A)), plus AFCI protection for most living-area circuits (NEC 210.12). A house wired in 1975 will legally have neither in most rooms — that is expected, not a defect — but the inspection should record what exists and what your insurer or remodel permit will demand.

Test every GFCI with its own test button. Note dead GFCIs, broken outdoor weather covers, and unprotected garage or basement circuits. For bedrooms and living rooms, check whether breakers are combination-type AFCI; standard breakers in a 2020-code jurisdiction are a code gap to price.

Budget reality: a GFCI receptacle swap is $15–$30 DIY or $100–$180 per device professionally; an AFCI breaker retrofit runs $60–$120 per breaker plus labor. Whole-house protection retrofits for a 30-circuit panel typically land in the $1,000–$2,500 range professionally installed.

Aluminum branch wiring and knob-and-tube

Two legacy wiring methods deserve their own line in your report. Solid aluminum branch-circuit wiring (common roughly 1965–1975, marked AL or ALUMINUM on the jacket) oxidizes and creeps at terminations, causing the loose-connection overheating behind many receptacle fires. It is not an automatic rewire — Copalum crimp or AlumiConn connector remediation at every termination, torqued per NEC 110.14(D), is the recognized repair — but unremediated aluminum with warm cover plates is a red flag.

Knob-and-tube (pre-1940s, open conductors on ceramic insulators) is safe when undisturbed and uninsulated-over, but blown-in attic insulation burying it is a fire hazard, splices are often soldered-and-taped outside boxes, and most insurers refuse or surcharge it. Assume any knob-and-tube you find is active until an electrician proves otherwise.

Get the insurance quote before removing contingencies — carriers flag both conditions. Our deep dive on aluminum branch wiring remediation explains the approved repair methods.

Boxes, splices, and receptacle condition

The small stuff reveals the quality of all hidden work. Every splice must live in an accessible, covered box (NEC 300.15, 314.29): open attic splices, buried boxes, missing cover plates, and extension cord used as permanent wiring all signal DIY work reaching further than you can see.

Receptacle checks: firm plug retention (loose slots arc — receptacles are cheap, replace them), no cracked faces, weather-rated outdoor boxes with covers, and nothing fed by lamp cord through walls. Count two-prong receptacles: each marks an ungrounded circuit to address.

Junction box fill is a subtler check — cramming too many conductors in a shallow box overheats splices. The fill rules of NEC 314.16 give each conductor size a volume allowance (2.0 cubic inches per 14 AWG, 2.25 per 12 AWG); a standard 18-cubic-inch box holds at most nine 12 AWG conductors. Stuffed boxes get flagged.

How to read the panel label like an inspector

The panel directory — the paper or printed label inside the door — is the map of the whole system. A good one names every circuit by room and load (“Kitchen receptacles N + S”, not “plugs”). A bad one says “misc” six times or is blank, which means nobody has traced the system in years and surprise circuits await your remodel.

Verify three things against the label: the main breaker rating (that is your service size — 100 or 200, stamped on the handle), the breaker sizes against wire sizes on a sample of circuits (15 A on 14 AWG, 20 A on 12 AWG per NEC 240.4(D) — a 30 A breaker on 14 AWG wire is an immediate hazard), and that dedicated loads actually have dedicated circuits (HVAC, water heater, laundry, kitchen appliance circuits).

Photograph the label and the breaker rows during the showing. An electrician reviewing photos can spot double-taps, alien breakers, and missing handle-ties on multi-wire circuits before you pay for a site visit. Learn the one-line language panels speak in our guide to reading single-line diagrams.

Red-flag table with repair cost ranges

FindingRed flag levelTypical fix (market estimate)
Federal Pacific Stab-Lok / Zinsco panelDeal-breaker / insure issueFull panel replacement $1,500–$3,000
60 A service, gas house, no EV plansNegotiateLive with it; upgrade later $2,500–$5,000
60–100 A + planned EV / heat pumpDeal math200 A upgrade $2,500–$5,000
Unremediated aluminum branch wiringNegotiate hardConnector remediation $2,000–$4,000
Active knob-and-tubeDeal-breaker for most buyersRewire affected areas $5,000–$15,000+
No grounding + no GFCISafety failGFCI retrofit $500–$2,000
Double-tapped / alien breakersFix before closeElectrician corrections $200–$600
Open splices, buried boxesWorkmanship warningBox and re-splice $150–$500 per location
30 A breaker on 14 AWG wireImmediate hazardCorrect breaker + inspect wire, $100–$300
Dead GFCIs / open grounds everywhereNegotiateDevice replacement program $500–$1,500

Ranges are US 2025–2026 market estimates for licensed work; permits, drywall repair, and region swing them ±40 percent. Use them to size credits, not as quotes.

What a proper inspection report includes

Insist on a written report with photos, not a verbal “looks fine.” Minimum contents: panel brand, main rating, and breaker inventory; service size and conductor material; grounding electrode and bonding verification; GFCI/AFCI inventory with test results; wiring-method identification by area (copper, aluminum, knob-and-tube, cloth-insulated); a load calculation against your planned loads; and a prioritized deficiency list split into safety hazards (fix now), code gaps (fix at remodel or sale), and capacity limits (plan upgrades).

Ask the inspector to state license number, standards referenced (NEC edition adopted locally), and limitations (which covers were removed, which areas were inaccessible). A report naming code sections signals real work; one repeating only “recommend licensed electrician” is a refund request.

Time the inspection before the general contingency expires so findings can still move the price — and bring your load plans for the calculation to test.

Common mistakes buyers make

  • Trusting a flipped house on looks. New receptacles and a fresh panel cover routinely hide original 1970s aluminum or splices without boxes. Cosmetic remodels deserve more electrical scrutiny, not less.
  • Letting the general inspector cover electrical. Generalists find symptoms; electricians find causes and price cures. $300–$500 for a dedicated visit is the cheapest money in the transaction.
  • Forgetting insurance and financing. Carriers and FHA/VA appraisers flag Stab-Lok, Zinsco, knob-and-tube, and 60 A fuse boxes. A house you cannot insure is a house you cannot buy.
  • Ignoring capacity for future loads. A 100 A service that barely covers today blocks tomorrow EV charger and heat pump. Price the upgrade path now.
  • Accepting “grandfathered” at face value. Existing installations may legally remain, but insurers, remodel permits, and your family safety do not grandfather. Know the difference between legal-to-keep and safe-to-ignore.

Map the panel directory onto a floor plan during the inspection — future you will thank present you. Try it free: open the GorkyCAD demo and sketch the circuits room by room.

Frequently asked questions

How much does an electrical inspection cost?

A dedicated residential electrical inspection typically runs $200 to $500 in 2025–2026 US markets, depending on house size and whether the panel schedule is mapped. That is separate from the general home inspection and routinely pays for itself in negotiated credits.

Will a Federal Pacific panel fail an inspection?

Any competent electrical inspection flags Federal Pacific Stab-Lok and Zinsco panels as replacement items due to documented breaker failure rates and insurance refusals. Expect a panel replacement credit of roughly $1,500 to $3,000 in negotiations.

Is 100 amp service enough for a modern house?

A 100 A service suits a gas-heated house without an EV charger. Add an EV charger (40–60 A), heat pump, or electric range and the NEC 220.82 load calculation usually pushes past 100 A — price a 200 A upgrade before closing.

Can aluminum wiring be fixed without a full rewire?

Yes. The recognized repair is approved connector remediation (Copalum crimp or AlumiConn connectors) at every termination, torqued to the listed value per NEC 110.14(D). Budget roughly $2,000 to $4,000 for a typical house.

Should I get an electrical inspection on a new build?

Yes, ideally before drywall (rough-in check) and at final. New work can still carry double-tapped neutrals, missing AFCI protection, and mislabeled directories — all cheap to fix before the walls close.