Bringing power into a house: overhead vs underground

Overhead supply costs less and builds faster; a buried cable is more reliable, lasts longer and keeps the plot tidy. There is no universally better method — the right choice depends on distance, soil, climate and the utility's requirements.

Author:GorkyCAD Team

Two methods: overhead and buried cable

An overhead service entrance runs from the nearest pole to the house through the air: a self-supporting insulated conductor to a wall bracket or a service mast, then down into the meter box. Everything is visible and accessible, which is both its strength and its weakness. A buried entrance instead runs in a trench — cable in a duct or rated for direct burial, with sand bedding, mechanical protection and a warning tape — surfacing at the metering point.

Both methods end at the same place: a meter and a main breaker, then the house panel. The difference is only in the path between the grid and that point, but the path dictates cost, vulnerability and appearance for decades. That is why the choice deserves a proper comparison rather than a default habit of the local crew.

Cost and build time

Overhead usually wins the first cheque: no trench, no reinstatement of lawns and driveways, and a crew finishes in hours rather than days. The hardware is simple — brackets, clamps and the conductor itself — and faults are found by looking up. Underground work adds excavation, bedding, ducts, warning tape and surface restoration, plus careful routing around existing utilities.

CriterionOverheadUnderground
Upfront costLower, minimal earthworksHigher, trench and reinstatement
Build timeHoursDays, weather and soil dependent
Fault locationVisual, fastNeeds instruments and digging
AppearanceWires across the plotNothing visible
Typical threatsWind, ice, trees, vehicles hitting polesExcavations, groundwater, rodents

Remember that the table compares typical cases. A rocky plot can make trenching prohibitively expensive, while a long span across someone else's land can make overhead impossible — site conditions decide.

Three factors drive the buried price most: trench length, soil, and what lies on top. Digging across a lawn is cheap; opening asphalt or paving is not, and rock or high groundwater add unpredictability. Overhead has its own multipliers: extra poles, clearing corridors, road-crossing approvals. An honest estimate is always tied to the specific plot, never to an internet 'average connection price'.

Reliability: weather versus digging

Overhead lines suffer from everything the sky delivers: gale-force wind, ice loading, falling branches and, in some regions, wildfires. Most overhead faults are spectacular but short-lived — crews see the break and repair it the same day. Underground cable ignores weather entirely, which is why districts with buried networks report far fewer storm outages.

The buried cable has its own enemies: careless excavation is the leading cause of damage, followed by soil settlement, groundwater and, occasionally, rodents. A duct, correct depth, warning tape and an as-built drawing with the route marked reduce this risk dramatically. In short: overhead fails more often but is fixed faster; underground fails rarely but each repair is an excavation project. For a house where every outage means no heating pump or water, the rarer failure usually wins.

Metering and the responsibility split

Wherever the cable comes from, the metering point is the legal heart of the entrance. Utilities commonly require the meter in an accessible box — on a pole, a facade or a standalone cabinet at the boundary — so that readings and seals do not depend on entering the house. The main breaker and surge protection usually live in the same cabinet or immediately downstream.

The connection agreement draws the line of responsibility: the utility typically owns the network up to the meter or the connection clamp, and the owner owns everything after it. Read this document before arguing about who pays for a repair. Any change of method — say, replacing an overhead drop with a buried cable — also needs the utility's approval, because the demarcation point and the metering arrangement may move with it.

The metering cabinet usually hosts the main breaker and surge protection as well: lightning-induced surges strike both methods, they only travel different paths. Choose a cabinet with spare room — voltage relays, surge devices and future feeds will ask for space later. A box packed tight on day one is a classic mistake paid for with a full replacement.

Which fits your case

Choose overhead when the pole is close, the budget is tight, the soil is rocky or the connection is meant as a staged solution before a full reconstruction. Choose underground when the plot's appearance matters, storms are frequent, trees overhang the route, or the distance makes poles and clearances awkward. Long-term owners building 'for decades' usually pick the trench; developers selling quickly often pick the air.

  • Measure the real distance from the pole to the metering point — length multiplies every cost.
  • Check the soil: rock, high groundwater and paved surfaces all push the price of trenching up.
  • Look up: trees, neighbouring buildings and road crossings complicate overhead routes.
  • Ask the utility early which metering location it accepts for each method.
  • Plan the internal route too: the cable must reach the house panel sensibly from either entry point.

Showing the entrance in the project

Whichever method wins, the entrance belongs in the design as a first-class element: source, metering, main breaker and the house panel in one engineering model. Routes and lengths come from the floor plan, the single-line diagram is generated from the model automatically, and the specification plus the materials-labour-VAT estimate follow the same data into a single PDF package.

Draw the demarcation point explicitly so that everyone — owner, installer, inspector — sees where the utility's responsibility ends. Keep the cable route, cross-section and installation method in the cable schedule rather than in someone's head. Tariffs are on the pricing page: start free in the editor, and move to Pro when the project needs full calculations, auto-panel and exports including PDF, DXF, XLSX, IFC, BCF and GLTF.

It is easiest to carry the entrance through the same route as the whole project: from floor plan to documentation set in seven steps — layout, loads, panel, single-line diagram, cable schedule, specification, estimate. The service entrance and metering enter the design first, not as an afterthought, so the cable route lands sensibly and the panel gets a correct supply point.

FAQ

Which is cheaper — overhead or underground?

As a rule of thumb, an overhead connection wins on upfront cost: fewer earthworks and shorter installation time. But compare lifetime costs too — storm repairs, tree trimming and eventual replacement can narrow the gap over the decades.

Which cable can be buried?

Only cable types rated for direct burial or duct installation may go underground, with mechanical protection and a warning tape above. The cross-section follows the load calculation with voltage-drop and short-circuit checks; the exact choice is fixed in the design, not at the trench edge.

Is a mast or bracket needed?

Often yes for an overhead connection: a mast or wall bracket gives the required clearance height where the building itself is too low or set too far back. The need is decided by geometry and the utility's rules, so confirm it before buying hardware.

Who replaces the service entrance?

Usually the utility owns the line up to an agreed demarcation point — often the meter or the connection clamp — and the owner owns everything downstream. The exact split is written in the connection agreement, so read that document before disputing any repair bill.