What does it cost to wire a house. Every customer asks, and every honest electrician answers with a range, not a number. The range exists because materials and labour split differently on every job: a concrete house with long runs is cable-heavy, a house with a big panel and many dedicated circuits is device-heavy, and old-wall retrofits are labour-heavy. This article gives you the breakdown method professionals use, with percentages, three worked scenarios, and rules for reading somebody else quote.

All prices here are 2026 planning ranges that move with copper and region. Use the method, not the numbers: count points, measure metres, schedule the panel, price grounding, then add labour by hours.

1. The four buckets, always in the same order

Estimate in four buckets so every bid is comparable. Points: every socket, switch, light, and fixed appliance with its circuit assignment. Metres: cable by cross-section measured along real routes with drops and slack. Panel: breakers, RCDs or GFCIs, enclosure, busbars, surge protection. Grounding: electrodes, grounding electrode conductor, clamps, bonding jumpers.

The discipline matters more than the tool. Two bids with the same four buckets can be compared line by line. Two bids as lump sums cannot be compared at all, which is exactly how customers end up choosing the cheaper-looking number that covers less work.

2. Points: counting what gets installed

Walk the plan room by room and number every point. A typical three-bedroom house of about 100 sq m has forty to sixty points: twenty to thirty sockets, ten to fifteen lights, five to eight switches, plus fixed loads such as cooker, air conditioner, water heater, and washing machine. Each point needs a box, a device, a share of cable, and labour minutes.

Price points in groups, not one by one. Socket point installed: device, box, share of 3x2.5 cable, and about one hour of combined first and second fix in masonry. Light point: device, box, share of 3x1.5, about forty minutes. Fixed loads are quoted individually because cable sizes and breakers differ.

3. Metres: the bucket everyone undercounts

Measure routes, not straight lines. From panel to the farthest socket, add horizontal run plus vertical drops of about 0.3 m at each end plus 10 percent slack. A run that looks like 12 m on paper is really about 14 m of cable. Across a house this adds fifteen to twenty percent over naive measurement, which is exactly the shortfall that kills Excel bids.

Worked calculation. Twenty-four sockets on six circuits, average route 14 m per circuit home run plus daisy chain: six circuits times 14 m is 84 m of 3x2.5 for trunks, plus drops and slack of roughly 20 percent gives about 100 m. At 1.8 per metre that is 180 for socket cable alone. Lighting adds another 60 m of 3x1.5 at 1.1 per metre, about 66. Cooker and air conditioner runs add 30 m of 4 to 6 sq mm at 3 to 5 per metre, about 120. Cable subtotal near 370 before conduit and trunking.

CableTypical usePlanning rate per mHouse example
3x1.5 sq mmLighting1.0 to 1.360 m, about 70
3x2.5 sq mmSockets1.6 to 2.1100 m, about 180
3x4 / 3x6 sq mmFixed loads3.0 to 5.530 m, about 120
Conduit + boxesContainmentlump 120 to 200about 160

4. Panel: the most underpriced bucket

The panel is quoted as one line far too often, hiding twelve to twenty devices. Schedule every breaker with rating and curve, every RCD with rating and tripping current, the main switch, busbars, enclosure with spare ways, and surge protection where required. A twelve-circuit house needs a 24-way board minimum with at least twenty percent spare capacity per good practice.

Budget guide for 2026: breakers 6 to 15 each depending on curve and poles, 30 mA RCDs 35 to 70, main switch 25 to 50, enclosure 80 to 200, SPD 60 to 150. A full twelve-circuit panel lands between 450 and 900 in materials. Labour for assembly, wiring, labelling, and testing adds six to ten hours. Testing alone deserves its own line: insulation resistance at 500 V DC with a minimum of 1 megaohm on each circuit group, continuity of protective conductors, and RCD trip-time tests at rated and five-times rated current per IEC 60364-6. Customers rarely question a testing line, but they always question a callback.

5. Grounding and bonding: small money, big liability

Grounding is three to eight percent of materials but one hundred percent of the safety argument. Count electrodes, grounding electrode conductor sized per NEC 250.66 or IEC 60364-5-54, clamps, inspection pits, and bonding jumpers to water, gas, and structural steel. Never let this bucket read zero: a bid without grounding is either incomplete or non-compliant.

Typical house: two electrodes, 15 m of grounding conductor, clamps and pit, bonding to services. Materials 80 to 180, labour half a day including testing of electrode resistance. State the measured value on handover; under NEC and IEC practice the installation must provide an effective grounding path, verified by test, not by assumption.

6. Labour: hours, not vibes

Convert points to hours with your own measured rates. Example rates for masonry: socket point 60 minutes total, light point 40 minutes, switch 30 minutes, panel assembly and testing 8 hours, grounding half day. Forty points plus panel plus grounding lands near sixty hours for one electrician, or about eight working days, plus helper time at lower rate for chasing and pulling.

Multiply by your loaded hourly rate, which includes insurance, transport, tools, vehicle wear, quoting time, and non-billable hours. The classic error is multiplying bare wages by hours and discovering the business lost money while the electrician earned his pay. Your rate must carry the shop, not just the hands.

Scenario, 2BHK equivalentMaterials shareLabour shareTypical total range
Budget rewire, surface runs45 percent55 percentLower band
Standard concealed, 100 sq m50 percent50 percentMiddle band
Premium, SPD + spares + testing55 percent45 percentUpper band

7. Three scenarios for a 2BHK equivalent

Scenario A, budget surface rewire of a two-bedroom flat: thirty points, one panel row reused, minimal chasing. Materials near 1,600 to 2,200, labour near 2,000 to 2,600. Scenario B, standard concealed wiring in a 100 sq m new house: fifty points, new 24-way panel, grounding set. Materials 4,500 to 6,000, labour 4,000 to 5,500. Scenario C, premium with surge protection, spare ways, full testing protocol, and labelled as-built documentation: add fifteen to twenty percent to scenario B.

Read these as bands for 2026 metro pricing. Rural work runs lower on labour, high-cost cities run higher on both. Copper price swings move the cable rows by ten percent in a quarter, so date every quote.

8. Mini-case: the quote that looked expensive and was not

A homeowner in Florida collected two quotes for a 110 sq m house: 8,400 lump sum and 9,700 itemised across the four buckets. The cheaper bid had no grounding line, no RCD schedule, and cable listed as one lump of 200 m. The itemised bid showed 340 m by size, twelve breakers with ratings, two 30 mA RCDs, and a grounding set with testing. During work the cheap contractor issued a 1,400 change order for the panel upgrade and grounding the inspector demanded. Final cost 9,800, two weeks late. The expensive bid was the cheaper job.

9. How to read somebody else estimate in ten minutes

Ask for the four buckets with numbers. Points count: if missing, the bid is not comparable. Cable metres by size: divide by points, expect six to ten metres per point; far outside means guessing. Panel schedule with breaker ratings and RCD types: absence of GFCI or RCD protection per NEC 210.8 or IEC 60364-4-41 is a defect, not a saving. Grounding scope with testing: zero means non-compliant. Spare ways: at least twenty percent, otherwise the first addition becomes a panel replacement.

A fourth pattern is worth naming: the allowance bid. Some contractors list cable as an allowance of 150 m with unit rates for extra metres. That is honest only if the unit rate is fixed in writing and measured jointly at the end. Without a fixed rate and a measurement rule, allowances become the most expensive lines on the job. Prefer measured totals; accept allowances only with signed rates.

10. Assumptions and where you must not economise

Assumptions: residential work under NEC or IEC 60364, copper conductors, masonry or drywall, licensed labour, 2026 price levels with regional adjustment. This method does not apply to hazardous locations, healthcare facilities, or medium-voltage installations. Never economise on five things: breaker-to-wire matching per NEC 310.16 ampacity, RCD or GFCI protection on required circuits, grounding electrode system with testing, spare panel capacity, and cable routing that respects separation and protection rules. Save money on fittings, finishes, and timing, never on protection.

Price your next house with the four-bucket method on a real plan instead of guessing: open the free demo at https://gorkycad.com/cad/?demo=1, no signup needed, and compare the generated list with your last bid.

Break down your next house into points, metres, panel, and grounding: free demo at https://gorkycad.com/cad/?demo=1, no signup needed.

Frequently asked questions

What share is materials vs labour in house wiring?

Roughly half and half for standard concealed work in 2026 metro pricing. Surface rewires skew labour-heavy, premium jobs with big panels skew materials-heavy. Always split the bid into buckets instead of trusting a single ratio.

How many metres of cable does a house need?

Expect six to ten metres per point measured along real routes with drops and slack. A fifty-point house lands near 300 to 400 m total across all sizes. Far outside that band means the takeoff was guessed.

Why are two quotes thousands apart?

Usually scope, not greed. The cheaper bid often omits grounding, RCDs, spare ways, or real cable metres. Compare the four buckets line by line and the gap usually explains itself.

Where must I never cut costs?

Breaker-to-wire matching per NEC 310.16, RCD or GFCI protection per NEC 210.8 or IEC 60364-4-41, the grounding system with testing, and spare panel capacity. Economise on finishes, not protection.

Can I estimate this from the plan automatically?

Yes. Draw the plan once in the free demo at https://gorkycad.com/cad/?demo=1 and generate points, metres, panel schedule, and grounding list from it, then price the four buckets.