A single line diagram (SLD) is the one drawing every inspector, utility engineer, and electrician asks for first. It shows the complete power path of a building on a single sheet: service entrance, meter, main breaker, distribution boards, feeders, branch circuits, protective devices, and earthing. If the SLD is wrong, the rest of the project documentation cannot be trusted.

An online SLD maker builds this drawing from a load list instead of manual drafting. You enter rooms, loads, and cable runs. The tool sizes breakers, checks cable ampacity, balances phases, and draws the standardized scheme automatically. This article explains what belongs on a permit-ready SLD, the exact build order, typical mistakes, a full worked calculation, and how the automated approach compares with drawing the same scheme manually in AutoCAD.

1. What a single line diagram actually shows

An SLD uses one line to represent a multi-conductor circuit. A three-phase feeder with neutral and earth (five conductors) appears as a single line with small tick marks indicating the number of conductors. Each segment carries a label with cable type and cross-section, for example 5x10 sq mm Cu, XLPE. Every switching and protective device appears as a standardized symbol with its rating next to it.

The drawing reads top to bottom, from source to load. At the top sits the utility service: voltage level, available fault current if known, and metering. Below comes the main disconnect, then surge protection, then distribution boards. Each board fans out into feeders and final branch circuits. Earthing connections and the main bonding jumper appear at the side, tied to the earth bar. Nothing decorative belongs here. Every element must match something installed and inspected.

2. What must be on a permit-ready SLD

Inspectors check a fixed minimum set. Missing any of these items is the most common reason for rejection. Your SLD must show the service characteristics (voltage, phases, system earthing type TN-S, TN-C-S, or TT), the main overcurrent device with rated current and breaking capacity, metering equipment, and the earthing arrangement with conductor sizes.

Each distribution board needs a designation, rated current, number of ways, and enclosure type. Each outgoing circuit needs a designation (Q1, Q2, and so on), the load name and rated power in kW, cable type and cross-section, installation method in abbreviated form, route length, design current, breaker rating and trip curve, and residual current device rating where required. Phase connections (L1, L2, L3) must be marked on every single-phase circuit so phase balance can be verified. A title block with project address, designer, date, revision, and scale completes the sheet.

SLD elementWhat to showExample
ServiceVoltage, phases, earthing, agreed power400 V, 3-phase, TN-C-S, 15 kW
Main deviceRating, poles, breaking capacity32 A, 4P, 6 kA
Branch circuitLoad, current, breaker, cable, length, phaseQ7, cooker 31.3 A, C32, 3x6, 14 m, L1
ProtectionRCD rating, type, selectivity40 A / 30 mA type A; 100 mA type S upstream

3. The correct build order: load list first

Never start by drawing symbols. Start with the load list. Walk through the building room by room and record every load: lighting points, socket outlets, cooker, oven, water heater, air conditioner, heat pump, washing machine, and any fixed equipment. For each load record the rated power, voltage, and whether it is single-phase or three-phase. Group small loads into circuits at this stage: lighting per floor or zone, sockets per room group, and dedicated circuits for every fixed appliance above 2 kW.

Next, compute the design current of each circuit. Then select protective devices, then cable cross-sections verified against installation method and derating, then assign circuits to phases, and only then draw the scheme. This order matters because every downstream choice depends on current. Drawing first and sizing later produces schemes where breakers do not match cables — the exact defect inspectors find in minutes.

4. Worked calculation: from kW to breaker and cable

Take a concrete branch circuit: a 7.2 kW electric cooker, single-phase, 230 V, power factor 1.0 (resistive load). Design current formula for single-phase loads: I = P / (U x cos phi). Substitute the numbers: I = 7200 / (230 x 1.0) = 31.3 A. The next standard breaker above 31.3 A in the IEC range is 32 A, curve C for a fixed resistive load.

Now verify the cable. A 6 sq mm copper cable with PVC insulation, installed in conduit in a wall (installation method B1 per IEC 60364-5-52 Table B.52.2), has a tabulated current-carrying capacity of 32 A at 30 C ambient. With no grouping derating (single circuit) and ambient 30 C (correction factor 1.0), the effective ampacity Iz = 32 x 1.0 x 1.0 = 32 A. The coordination rule is Ib <= In <= Iz: 31.3 <= 32 <= 32. It holds exactly, so 6 sq mm is acceptable here; in practice many designers step up to 10 sq mm for voltage drop margin on long runs. Repeat this exact chain — current, breaker, cable, coordination check — for every circuit before drawing anything.

Load (kW)Current 230 V 1-ph (A)BreakerCable Cu, B1 (sq mm)
2.0 sockets9.1C162.5
3.0 oven13.0C162.5
7.2 cooker31.3C326
9.0 shower39.1C4010

5. Three-phase example: feeder sizing and phase balance

Now a three-phase case: a small house with a 15 kW agreed load, 400 V three-phase, overall power factor 0.9, demand factor 1.0 at the service entrance. Formula: I = P / (sqrt(3) x U x cos phi). Substitute: I = 15000 / (1.732 x 400 x 0.9) = 15000 / 623.5 = 24.1 A. A 32 A four-pole main breaker (curve C or D per utility rules) covers this with margin for motor starting currents.

Phase balance is checked by summing single-phase loads per phase. Suppose after grouping: L1 carries 5.2 kW, L2 carries 4.8 kW, L3 carries 5.0 kW. Convert each at 230 V and cos phi 0.95: L1 = 5200 / (230 x 0.95) = 23.8 A; L2 = 4800 / 218.5 = 22.0 A; L3 = 5000 / 218.5 = 22.9 A. Unbalance between the heaviest and lightest phase is (23.8 - 22.0) / 23.8 = 7.6 percent, well within the 15 percent practical limit used by most designers. If one phase exceeded the others by more than 15 percent, move one socket circuit to the lighter phase and recompute.

6. Breaker, RCD, and cable schedule on the SLD

Every circuit on the SLD carries three coordinated numbers: design current Ib, breaker rating In, and cable ampacity Iz. For socket circuits in dry rooms, add 30 mA residual current protection (RCD type A for circuits with electronics, per IEC 60364-4-41). For wet rooms, bathrooms, and outdoor circuits, 30 mA RCD protection is mandatory with no exceptions. Upstream, a selective 100 mA or 300 mA type S device provides discrimination so a fault in one bathroom circuit does not black out the whole house.

Cable cross-sections follow from NEC 310.16 or IEC 60364-5-52 ampacity tables after derating for ambient temperature and grouping. A 2.5 sq mm copper conductor (method B1, two loaded conductors) carries 24 A tabulated; with four grouped circuits (grouping factor 0.65) the effective capacity drops to 15.6 A — below a 16 A breaker. That combination fails coordination, and the SLD must show either 4 sq mm cable or fewer grouped circuits. The SLD makes this visible at a glance because Ib, In, and cable size sit side by side in the load table under the scheme.

7. Typical mistakes that fail inspection

First, breakers without cable verification: a C32 breaker drawn on a 2.5 sq mm cable. The coordination rule fails and the inspector rejects the sheet. Second, missing RCDs on socket and outdoor circuits, or a single RCD for the whole house with no selectivity. Third, no phase marking on single-phase branches, so balance cannot be checked. Fourth, cable labels without installation method: 2.5 sq mm means 24 A in free air but only about 18.5 A buried in thermal insulation, so the number alone proves nothing.

Fifth, neutral and earth handling errors: undersized neutral on circuits with heavy harmonics, or a missing main bonding jumper to water and gas pipes. Each of these is a one-line fix on the SLD but a full day of rework on site. A generator that derives the SLD from the same model as the cable schedule cannot produce the first four errors, because the numbers come from one calculation, not from retyping.

8. Online generator versus manual AutoCAD drafting

Manual drafting in AutoCAD gives full graphic freedom but zero electrical intelligence. You draw every breaker symbol by hand, type every rating, and retype the same data into a separate spreadsheet for the panel schedule. Each transcription is a chance for mismatch: the scheme says C20, the spreadsheet says C16, the cable schedule says 2.5 sq mm on a 20 A circuit in insulation. Coordination studies of manually drawn residential projects routinely find 3 to 7 such mismatches per 30-circuit scheme.

An online generator inverts the workflow: one model holds circuits, currents, devices, and cables, and the SLD, schedules, and bill of materials are views of that model. Change the cooker to 9.0 kW and every view updates together. For permit purposes that rigidity is an advantage: uniform sheets read faster.

9. Mini-case: 100 sq m house, 28 circuits, one afternoon

A two-storey house, 100 sq m, all-electric with a 9 kW cooker, 6 kW water heater, two air conditioners at 2.5 kW each, and standard lighting and sockets. Load list totals 24.6 kW connected; with a demand factor of 0.5 the design load is 12.3 kW. At 400 V three-phase and cos phi 0.92: I = 12300 / (1.732 x 400 x 0.92) = 12300 / 637.4 = 19.3 A per phase at the service. A 32 A main breaker with 10 sq mm service cable leaves margin for one future heat pump circuit.

The 28 branch circuits split 10/9/9 across L1/L2/L3 with unbalance under 10 percent. Drafting time in the generator is about 75 minutes total; the same package drawn manually takes two to three working days.

10. Assumptions and when this method does not apply

This guide assumes standard low-voltage installations up to 400 V, copper conductors with PVC or XLPE insulation, ambient temperatures 25 to 35 C, TN earthing systems, and linear or mildly non-linear loads where cos phi is a fair description. Derating factors used here (grouping 0.65 for four circuits, temperature 1.0 at 30 C) come from IEC 60364-5-52 and NEC 310.16 notes.

The method does not directly apply to medium-voltage systems, aluminum conductors without terminal correction, installations above 1000 m altitude without correction, ambient temperatures above 40 C, circuits with heavy harmonic content requiring neutral oversizing, or TT systems where earth loop impedance governs disconnection times. For those cases use the full standard text and a licensed engineer review, then record the scheme the same way.

11. Checklist before you submit the SLD

Verify five things: every circuit has Ib, In, cable size, length, and phase; Ib <= In <= Iz holds on every row; RCDs cover sockets and wet rooms with selectivity; unbalance is within 15 percent; the title block and earthing details are filled in. Build it once from a real load list and the SLD becomes the contract between design and inspection.

Build your SLD in minutes — open the free demo at https://gorkycad.com/cad/?demo=1, enter loads, and export a permit-ready single line diagram as PDF.

Frequently asked questions

Do I need an SLD for a small house extension?

In most jurisdictions yes for any new circuit work submitted for permit or utility connection. Even where not formally required, inspectors and insurers ask for it. A small extension needs a one-board SLD with the new circuits, cable sizes, and protective devices marked.

What is the difference between an SLD and a wiring plan?

The SLD shows the electrical topology: sources, boards, circuits, devices, and ratings on one schematic sheet. A wiring plan shows physical routing on the floor plan. You need both: the SLD proves correctness, the plan proves installability.

Which standard governs SLD symbols?

IEC 60617 (international) and ANSI Y32.2 / IEEE 315 (North America). Use one library consistently on a project. Mixing IEC contact symbols with ANSI breaker symbols on one sheet is a common rejection reason.

Can I generate an SLD automatically from a load list?

Yes. Enter loads per room, group them into circuits, and the tool computes currents, selects breakers, checks cables, and draws the scheme. Manual review of phases and RCD selectivity is still required before submission.

How often should the SLD be updated?

On every change of loads, breakers, or cable sizes — same revision cycle as the project. A common failure is an SLD from March with a panel schedule from June. Generate both from one model so they cannot drift apart.