Every foreman knows the scene: the drawing says RK-7, the site has three boxes marked RK-7, and nobody knows which cable is which. Labeling and the cable schedule exist to prevent exactly this. A label identifies the physical object; the schedule says where each cable starts, where it ends, what it is, and how it is laid. When both follow one system, the drawing matches the site — and fault-finding takes minutes instead of hours.

This guide gives that system: designation structure per IEC 81346-2, schedule columns that survive handover, and marking practice that lasts. Norms cited: IEC 81346-2 (designation), IEC 60364-6 (verification records), BS 7671 Part 6 (schedules of inspections and test results).

1. Why labels fail on real sites

Labels fail for three repeatable reasons. First, no system: each electrician invents marks (RK7, R-7, P7 for the same box) so the schedule cannot match the wall. Second, labels that do not survive: marker pen on PVC tape fades in a year, paper tags tear during pulling, and unprinted heat-shrink slides off. Third, schedules written after the fact from memory instead of during installation — conductor counts and routes drift from reality within days.

The fix is boring but effective: one designation system fixed before first fix, printed labels applied as objects are installed, and the schedule updated the same day cable is pulled. Everything below implements that.

2. IEC 81346-2 designation in plain language

On larger jobs the full designation also carries the function aspect (=) for the system the object serves, for example =L lighting versus =P power, placed before the location and product parts. You rarely need it on houses and small shops, but keep the slot reserved: when the client later adds emergency lighting or a generator section, you extend the same structure instead of inventing a parallel one. The key discipline is that the product code always means the same physical thing everywhere — RK is always a box, never a breaker on one sheet and a box on another.

IEC 81346-2 structures every object designation from aspects: function (=), product (−), and location (+). On a small installation the full form is overkill, so use the site short form consistently: location prefix + product code + sequential number. Example: +L1−RK7 means floor L1, distribution box number 7. On drawings the short form RK7 is acceptable only if the location aspect is fixed for that sheet and stated in the title block — otherwise keep the full form.

Fix the alphabets once per project and never improvise: RK = junction/distribution box, QF = breaker, QD = RCD, WH = meter, XS = socket outlet, EL = luminaire, KL = cable line, GB = earth bar. Publish the list on sheet one (general data) so the client, the inspector, and the next contractor read the same language.

3. The designation table: object to mark

ObjectDesignation exampleMarked where
Distribution board+L1−GB1 (main board)door inside + schedule
Junction box+L1−RK7cover + inside lid
Socket circuit outlet+L1−XS12faceplate rear + schedule
Luminaire+L1−EL23yoke + schedule
Breaker in board+L1−GB1:QF6device + board schedule
Cable line+L1−KL14both ends + schedule
Earth bar+L1−GB1 (PE)bar + test sheet

Local practice may use a national alias alongside (for instance MAIN for the main board) — keep it as an alias in the schedule, never as a replacement. One object, one IEC designation; aliases listed, not used for identification.

4. Cable schedule columns that survive handover

A schedule with only from/to/section is a packing list, not a engineering document. The minimum column set that still works five years later: line mark (KL14), from (designation + room), to (designation + room), cable type and section (e.g. VVGng-LS 3×2.5), length in metres (measured, not estimated), laying method (conduit/trunking/buried with size), breaker and RCD (QF6/C16, QD2/40/30 mA), circuit load in amps, and remarks (spare cores, date, installer initials).

LineFrom → ToCableLengthLaidProtectionLoad
KL14GB1 → RK7 (corridor)3×2.518.4 mPVC 20 mmQF6 C16 / QD211.5 A
KL15GB1 → XS12 (bedroom 2)3×2.524.7 mPVC 20 mmQF7 C16 / QD29.2 A
KL16GB1 → EL23 (kitchen)3×1.521.3 mPVC 16 mmQF3 B10 / —3.1 A
KL17GB1 → cooker XS203×612.8 mPVC 25 mmQF16 C32 / QD527.4 A

Lengths come from the plan measure tool or a measuring wheel, rounded up 3 percent for terminations — never guessed. Protection entries name the actual devices (QF6, not just 16 A) so the schedule doubles as the test sheet index at commissioning.

5. Worked mini-schedule: one room, four lines, zero ambiguity

Given: bedroom 2 needs two socket outlets (XS12, XS13 on one radial), one luminaire (EL23 fed from the corridor lighting circuit), and one spare conduit for future air-conditioning. Calculation: radial load 2 × 16 A sockets at 0.2 diversity ≈ 6.4 A plus margin → 2.5 mm2 on C16; lighting 3 × 9 W LED ≈ 0.12 A → 1.5 mm2 on B10; spare conduit 25 mm empty with draw wire.

Schedule rows: KL15 (GB1 → RK7 → XS12/XS13, 3×2.5, 24.7 m, PVC 20, QF7 C16/QD2, 6.4 A); KL16 branch (RK7 → EL23 loop from lighting board section, 3×1.5, 9.6 m, PVC 16, QF3 B10, 0.4 A share); KL-SPARE (GB1 → bedroom wall, empty PVC 25 with draw wire, 22.0 m, no protection yet, marked SPARE — DO NOT ENERGIZE). Every row has both ends labeled before the cable is pulled, and the spare is recorded as spare, not left as a mystery tube.

6. Marking practice that lasts ten years

Use printed self-laminating wire markers or heat-shrink print sleeves on every conductor end, printed box labels under clear cover on every box lid, and engraved or printed traffolyte plates on boards — never hand-written tape as the final mark. Minimum text height 3 mm on wire markers, 5 mm on box lids, 8 mm on board schedules. Fix cable tags at both ends within 150 mm of the termination and at every intermediate box the cable passes through.

Photograph every board and every open box before closing: the photo file name carries the designation and date (for example GB1_2026-05-12.jpg) and goes into the handover folder. Five years later that photo is worth more than any memory.

7. Keeping drawing and site in sync during the job

Assign one person as the schedule keeper — usually the foreman — and give only that person the editable file. Everyone else works from printed copies or read-only PDFs dated the same day. Parallel edits by three people produce three schedules that disagree on KL numbers by Monday morning. When a route changes, the keeper updates the length, the laying method, and the remarks in one pass, then reprints the affected sheets with the new revision letter.

Change the schedule the day the change happens, not at the end of the job. Rule: no cable is pulled without a schedule row, no schedule row is closed without both end labels photographed, and no device is moved without updating the plan revision cloud and the schedule remarks column the same day. Hold a 10-minute Friday reconciliation: foreman reads the schedule aloud, installer confirms each row against the wall.

Version the schedule with the drawing revision (Rev C schedule matches Rev C plans). A schedule marked Rev B against Rev D plans is the most common cause of test-day confusion — the wires are right, the paper is wrong.

8. Mini-case: 40 cables, zero hunting

A two-floor house had 40 cable lines across lighting, sockets, cooker, air-conditioning spares, and garden supply. Every line got a KL number at first fix, both ends tagged before pulling, schedule rows written the same evening with measured lengths. At commissioning, loop testing 40 lines took one tester-day with zero identification faults; the inspector picked 6 random lines and all 6 matched the schedule first try. At the first fault call two years later (a tripping socket radial), the owner read KL15 off the schedule over the phone and the electrician arrived with the right breaker and cable data. Total extra time at first fix: about two hours of labeling against a week of avoided hunting.

9. Assumptions and when this does not apply

This system assumes a project up to about 100 lines with one contractor, printed label stock available, and drawings that carry revision control. It does not apply to: (1) utility and industrial plants with owner-mandated KKS or plant tag systems — follow the plant standard; (2) fire-alarm, security, and BMS cabling, which have their own addressing schemes; (3) very small jobs (one room, three lines) where a full KL schedule is overhead — a marked-up plan plus box labels suffice; (4) existing buildings with legacy marks the client refuses to change — record old and new marks side by side; (5) jurisdictions requiring specific statutory labels (e.g. bilingual safety marking) — add them alongside, not instead.

See also

Draw the system with single-line diagram maker and how to read a single-line diagram, fill the boards with panel schedule template, and size every line with cable size from amps and kW.

Try it on your own plan — open the free demo at https://gorkycad.com/cad/?demo=1, no registration needed.

Frequently asked questions

What does IEC 81346-2 require for labels?

A consistent designation built from aspects — function, product, and location (for example +L1-RK7 for floor L1, box 7). The standard fixes the structure, not the national abbreviations: publish your letter codes once on sheet one and use them everywhere without improvisation.

What columns must a cable schedule have?

At minimum: line mark, from and to designations with rooms, cable type and section, measured length, laying method, protective devices by mark (QF/QD), circuit load in amps, and remarks with date and initials. From/to/section alone is not a schedule.

How do I label both ends of a cable?

Tag within 150 mm of each termination and at every intermediate box, with the line mark (KL14) plus the far-end designation. Use printed self-laminating or heat-shrink markers — hand-written tape is temporary, not a final mark.

How do I stop the drawing and site drifting apart?

Pull no cable without a schedule row, photograph both end labels the same day, update plan and schedule revisions together, and reconcile weekly. Version the schedule with the drawing revision so Rev C paper never describes Rev D walls.

What if the site uses old legacy marks?

Do not overwrite them unilaterally. Record old and new marks side by side in the schedule remarks column, label new work in the IEC system, and agree the cutover with the client in writing before renaming anything live.