Office renovation electrics fail in quiet ways: the new meeting room has two outlets for eight laptops, the IT rack shares a breaker with the kitchenette kettle, and the air conditioners trip the lighting circuit on the first hot day. Tenants notice all of it within a week.

This guide gives contractors and small design offices a working method: per-employee loads, lighting power density, separate IT and HVAC circuits, panel sizing, and a worked 200 sq m example. Code references are NEC Articles 210/220 with IEC 60364 notes for international practice.

1. Start from headcount and zones, not from outlets

An office is people plus zones. Count workstations first, then meeting rooms, kitchenette, server corner, and HVAC. A 200 sq m office for 24 people has roughly 24 workstations at 150–250 W each of IT plus monitors, 2–3 meeting rooms, one kitchenette, and 3–5 split AC units. That inventory drives everything: circuit count, panel size, and cable routes.

Draw zones before circuits. Workstations along the facade need floor boxes or dado trunking; meeting rooms need wall outlets plus table feeds; the kitchenette and the AC condensers need their own lines from day one, never shared with desks.

2. Load per employee: a honest number

Plan 300–500 W per desk position of connected IT load: desktop or laptop with two monitors (80–150 W), phone charger and desk lamp (20–40 W), plus a share of printers and network gear. With a diversity factor of 0.6–0.7 across 24 desks, 24 × 400 W × 0.65 ≈ 6.2 kW of real workstation demand — small enough for a few 20-A circuits, large enough to matter when it all lands on one breaker.

Add meeting rooms at 500–1000 W each (display, video bar, laptop charging for six), kitchenette at 4–6 kW connected (kettle 2 kW, microwave 1.2 kW, fridge 0.2 kW, dishwasher 2 kW — never simultaneous, but the circuit must survive the kettle plus microwave moment), and network rack at a steady 0.5–1.5 kW.

3. Lighting power density without over-lighting

NEC 220.12 caps lighting load calculations by occupancy (offices around 1.3 W/sq ft / 14 W/sq m in older tables; newer energy codes push to 0.9–1.0 W/sq ft). For a 200 sq m (2150 sq ft) office that means roughly 2.0–2.8 kW of lighting load allowance. With modern LED panels at 100–130 lm/W and a target of 300–500 lux (IES / EN 12464-1), real installed power lands near 1.5–2.0 kW — inside the allowance with margin.

Zone the lighting with the renovation: open space on daylight sensors near windows, meeting rooms on dimmers or scenes, corridors and toilets on occupancy sensors. Lighting controls are the cheapest energy saving in a retrofit and often mandatory under local energy codes.

4. Separate the lines that must never share

Four systems stay independent. IT workstation circuits stay off kitchenette and cleaning circuits. The server/network rack gets its own dedicated circuit, ideally with a small UPS upstream. Air conditioners each get dedicated circuits from the panel — a 3.5 kW split draws 15 A at 230 V single-phase, and three of them on a shared 20-A line is a guaranteed summer trip. Emergency and exit lighting stays on its own protected circuit where required.

Physically separate data from power as well: keep structured cabling 200 mm or more from parallel power runs, cross at right angles, and never share trunking compartments without a divider (IEC 60364-5-52 segregation practice).

5. Panel schedule for the example office

The table below is a realistic starting schedule for the 200 sq m / 24-person office. Adjust breaker sizes to nameplates, but keep the grouping logic.

CircuitLoad servedBreakerWire (copper)
L1–L2Workstations zone A/B (12 desks each)2× 20 A 1-pole12 AWG / 2.5 sq mm each
L3Meeting rooms (3 rooms + displays)20 A 1-pole12 AWG / 2.5 sq mm
L4Server rack + network (dedicated)20 A 1-pole12 AWG / 2.5 sq mm
L5Kitchenette (kettle + microwave diversified)20 A 1-pole GFCI12 AWG / 2.5 sq mm
L6–L8AC units 3× 3.5 kW3× 20 A 1-pole dedicated12 AWG / 2.5 sq mm each
L9–L10Lighting open space / rooms+corridors2× 15–16 A 1-pole14 AWG / 1.5 sq mm
L11Cleaning + spare20 A 1-pole12 AWG / 2.5 sq mm

6. Worked calculation: 200 sq m demand

Connected: workstations 24 × 400 W = 9.6 kW; meeting rooms 3 × 800 W = 2.4 kW; kitchenette 5.5 kW; rack 1.0 kW; AC 3 × 3.5 kW = 10.5 kW; lighting 2.0 kW. Total connected ≈ 31 kW.

Apply diversity: workstations 9.6 × 0.65 = 6.2 kW; meeting rooms 2.4 × 0.5 = 1.2 kW; kitchenette 5.5 × 0.6 = 3.3 kW; rack 1.0 × 1.0 = 1.0 kW; AC 10.5 × 0.9 = 9.5 kW (summer coincidence is real); lighting 2.0 × 0.9 = 1.8 kW. Demand ≈ 23 kW. On 400Y/230 V three-phase at cos φ 0.9: I = 23,000 / (1.732 × 400 × 0.9) ≈ 37 A per phase balanced. A 63-A three-phase board with a 40–50 A main and 24–36 ways covers this office with growth room; feed it with 5× 10–16 sq mm copper depending on length and voltage drop.

SystemConnected kWDiversityDemand kW
Workstations9.60.656.2
Meeting rooms2.40.501.2
Kitchenette5.50.603.3
Rack1.01.001.0
AC (3 units)10.50.909.5
Lighting2.00.901.8
Total31.0—23.0

7. Mini-case: the kettle that killed the servers

A 15-person office ran desks, the rack, and the kitchenette off two 20-A circuits "temporarily" after a refit. It worked until someone ran the 2 kW kettle while the microwave reheated lunch: 3.2 kW plus 2 kW of desks on one 20-A (4.6 kW max at 230 V) circuit. The breaker tripped, the rack lost power for four minutes, and the RAID array spent the weekend rebuilding.

The permanent fix took one morning: a dedicated rack circuit with a 1500 VA UPS, a separate kitchenette GFCI circuit, and desks split across two breakers by zone. The UPS now bridges the rare trip, and the rack never shares a breaker with anything that heats water or food. Total cost was less than one day of the office standing idle.

Budget the invisible half. Tenants see outlets and light fixtures; the money hides in trunking, core drilling, out-of-hours work, and making good. As a 2026 planning range, a straightforward 200 sq m fit-out runs roughly $80–150 per sq m for electrical work depending on city, access, and how much floor and ceiling must be opened — confirm against two local quotes before signing, because night-work premiums and listed-building constraints can double it.

8. Five renovation mistakes

First, one circuit per room instead of per system — rooms change use, systems do not. Second, floor boxes placed before furniture layout — half end up under cabinets. Third, AC condensers wired by the HVAC crew onto the nearest lighting circuit. Fourth, data and power in one undivided trunking — noise complaints and inspection remarks. Fifth, no spare ways in the panel — the next tenant improvement starts with a sub-panel and a mess.

9. Assumptions and when this does not apply

This guide assumes a tenant fit-out up to about 500 sq m on a 230/400 V system under NEC or IEC commercial practice, with standard split AC rather than central VRF. It does not cover data centers, trading floors with redundant A/B feeds, medical offices (Article 517 / IEC 60364-7-710), or buildings where the landlord dictates house panels, metering, and fire-alarm interfaces.

Permits differ by city: some require licensed-contractor-only panel work, arc-fault protection in certain occupancies, or energy-code lighting documentation. Confirm the local amendment set before rough-in.

10. Handover checklist

Label every breaker by zone and system, not by room number alone. Test every GFCI and every UPS transfer. Record as-built routes for floor boxes and trunking — the next refit will thank you. Leave 25 percent spare ways and a one-page load summary inside the panel door with the date, so the next contractor sizes additions from facts instead of guesses.

Route before you pull. Floor boxes belong on the furniture plan, not the reflected ceiling plan: confirm desk positions with the tenant, then run dado trunking or floor screed conduits so every box lands within 2 m of a desk cluster. Keep a 200-mm separation between parallel power and data runs, cross at right angles, and photograph every buried route before the screed covers it — those photos save half a day on every future refit. At commissioning, clamp-meter each phase at midday peak, record the readings on the load summary with the date, and torque-check terminations after the first week of thermal cycling.

See also:

See also: Commercial Lighting Load (VA per Sq Ft), Panel Schedule Generator Template, Single-Line Diagram Maker Online.

Sketch the zones once and get the panel right: open the free demo at https://gorkycad.com/cad/?demo=1, place panels, desks, and AC units, and export the schedule with the single-line diagram.

Plan an office fit-out with panels, circuits and data — try the free demo at https://gorkycad.com/cad/?demo=1

Frequently asked questions

How many watts per office employee should I plan?

Plan 300–500 W of connected IT load per desk and apply 0.6–0.7 diversity across the floor. For 24 desks at 400 W that is about 6.2 kW of real workstation demand.

Can workstations share a circuit with the kitchenette?

No. Kitchenette, IT rack, and air conditioners each need dedicated circuits. A kettle plus microwave alone can take most of a 20-A circuit.

What lighting load should I allow for 200 sq m?

Around 2.0–2.8 kW by code allowance, with real LED installs near 1.5–2.0 kW for 300–500 lux. Zone it with sensors and dimmers.

What size panel does a 200 sq m office need?

The worked example lands near 23 kW / 37 A per phase, so a 63-A three-phase board with 24–36 ways and a 40–50 A main is the practical answer with growth room.

Can power and data share trunking?

Only with a divider and segregation — keep 200 mm or more from parallel power runs and cross at right angles per IEC 60364-5-52 practice.