GB 50054-2011 Code for design of low-voltage electrical installations — translation

Clause-by-clause translation of the Chinese standard GB 50054-2011: selection of apparatus and conductors, protection against electric shock, circuit protection, cable installation. All key clauses with numbers.

🇷🇺 PUE — Rules for Electrical Installations (7th ed.)🕰️ PUE-6 — Rules for Electrical Installations (6th ed., 1985)🇺🇸 NEC — National Electrical Code (NFPA 70)🇪🇺 IEC 60364 / HD 60364 (EU national codes)🌎 NOM-001-SEDE, NBR 5410, AEA 90364, RETIE, NCh 4, CNE🇨🇳 GB 50054, GB 50303, JGJ 16, GB/T 16895 (IEC 60364)🇮🇳 IS 732

Document

DocumentGB 50054-2011 Code for design of low-voltage electrical installations
Edition2011
StatusCurrent (mandatory, GB)
Issued byMinistry of Housing and Urban-Rural Development of China (MOHURD)
Applies toDesign of low-voltage AC 50 Hz installations up to 1000 V in new, renovated and expanded buildings

Document structure

№Chapter / section
1General provisions
2Terms
3Selection of apparatus and conductors
4Arrangement of distribution equipment
5Protection against electric shock
6Protection of distribution circuits
7Wiring of distribution circuits
AAnnex A — k factors
GB 50054-2011 Code for design of low-voltage electrical installationsGB 50303-2015 Acceptance of building electrical worksJGJ 16-2008 Electrical design of civil buildingsGB 50096-2011 Residential design code, section 8GB 50057-2010 Building lightning protection codeGB 51348-2019 Civil buildings electrical design standardGB 50168-2018 Cable line installationGB 50052-2009 Supply reliability (China)GB 50058-2014 Explosive atmospheres (China)

Overview

GB 50054-2011 (低压配电设计规范) came into force on 1 June 2012, replacing GB 50054-95. It applies to AC 50 Hz installations up to 1000 V. The document has 7 chapters and 1 annex. Seven clauses are mandatory: 3.1.4, 3.1.7, 3.1.10, 3.1.12, 3.2.13, 4.2.6, 7.4.1.

Note: ampacity tables refer to GB/T 16895.15 — the Chinese adoption of IEC 60364-5-523. The code is harmonized with IEC.

Chapter 3. Selection of apparatus (3.1)

3.1.1 Apparatus must suit the environment, frequency, voltage; rated current ≥ calculated current; withstand dynamic and thermal short-circuit stresses; have adequate breaking capacity.

3.1.3 Isolating devices (all poles) for maintenance and testing; anti-mistake provisions where wrong operation is dangerous.

3.1.4 (mandatory) In TN-C systems the PEN conductor must not be disconnected; PEN must not be connected through switching apparatus.

3.1.7 (mandatory) Semiconductor devices must not be used as isolating devices.

3.1.8–3.1.10 Every controlled part needs a functional switching device; isolators, fuses and connector strips must not serve as functional switches (3.1.10 mandatory).

3.1.11 RCD selection: must open all live conductors (except TN-S with reliably earthed neutral); rated non-tripping current must exceed expected leakage; type per GB/Z 6829.

3.1.12 (mandatory) When an RCD is used for indirect-contact protection, a protective conductor is mandatory.

3.1.13 In TT systems a single RCD protecting the whole installation must be at the intake (unless Class II equipment).

3.1.14 In IT systems the RCD non-tripping current ≥ first earth-fault current.

3.1.17 IT systems require continuous insulation monitoring (250/500/1000 V test voltage, 0.5/0.5/1.0 MΩ setpoints).

Chapter 3. Selection of conductors (3.2)

3.2.2 Cross-section: ampacity ≥ calculated current; protection coordination; thermal/dynamic stability; voltage drop; mechanical strength. Minimum fixed copper sections: 1.5 mm² in conduit/trunking; bare on insulators — copper 10 mm², aluminium 16 mm².

3.2.3 Max insulation temperatures: PVC 70 °C, XLPE/EPR 90 °C, MI 105 °C (inaccessible) / 70 °C.

3.2.7 Neutral sized as phase when phase ≤ 16 mm² copper / ≤ 25 mm² aluminium, and in all single-phase two-wire circuits.

3.2.10 Minimum PEN: copper 10 mm², aluminium 16 mm².

3.2.12 PEN split: separate PE and N terminals/busbars; PEN first to the PE busbar; N must not bond to other earthed parts.

3.2.13 (mandatory) Extraneous conductive parts must not be used as PEN.

3.2.14 PE sizing: ≤16 mm² — same as phase; 16–35 mm² — 16 mm²; >35 mm² — half of phase. Separate PE: copper 2.5 mm² (protected) / 4 mm² (unprotected); equipment leakage >10 mA — 10 mm² copper.

3.2.15–3.2.17 Equipotential bonding: main — copper 6–25 mm²; supplementary/local — ≥ half of the largest PE in the zone, max 25 mm².

Chapter 4. Distribution equipment layout

4.2.1 Floor panels raised ≥50 mm indoors, ≥200 mm outdoors; sealed bases against rodents.

4.2.6 (mandatory) Bare live parts over walkways ≥ 2.5 m; below — barriers IP2X with bottom edge ≥2.2 m.

4.3.2 Rooms over 7 m long need two exits; doors open outward.

4.3.7 Openings protected with IP3X mesh against rodents.

Chapter 5. Protection against electric shock

5.1.2 Accessible bare live parts above 25 V must be enclosed to IP2X (IPXXB).

5.1.12 RCD ≤ 30 mA as additional protection against direct contact.

5.2.4 Main equipotential bonding in every building: PE/PEN, earthing terminal, metal water/gas pipes, building steelwork.

5.2.8–5.2.9 TN disconnection: 0.4 s at 220 V, 0.2 s at 380 V; fixed equipment — 5 s max.

5.2.13 If a breaker cannot meet TN times — use an RCD.

5.2.15 TT: RA × Ia ≤ 50 V.

5.2.19–5.2.24 IT: first fault — alarm (no disconnection); insulation monitoring mandatory; second fault — disconnect in 0.4–0.8 s; IT should not distribute N.

5.3.2 SELV/PELV ≤ 50 V AC.

5.3.11 SELV plugs/sockets incompatible with other systems, no PE contact.

Chapter 6. Circuit protection

6.1.1 Every distribution circuit needs short-circuit and overload protection.

6.2.4 For breakers, fault current at the line end ≥ 1.3 × instantaneous/short-delay trip setting.

6.2.5 SC protection at circuit start and at conductor-size reductions; max 3 m unprotected run.

6.3.3 Overload: IB ≤ In ≤ Iz and I2 ≤ 1.45 × Iz.

6.4.3 Fire-protection RCD: ≥ 300 mA, opens all live conductors.

Chapter 7. Wiring

7.1.3 Max 8 wires in one conduit (multiple lighting circuits).

7.2.1 Direct wiring: sheathed cable ≤ 6 mm²; heights 2.5/1.8 m; no embedding in plaster.

7.2.8 Attics with combustibles: metal conduit/trunking only.

7.2.9 All conductors of a circuit in the same conduit/trunking.

7.2.11 Clearances to hot pipes: 0.2/0.3 m (DHW below/above), 0.5/1.0 m (steam).

7.2.14 Conduit/trunking fill ≤ 40%, ≤ 30 conductors.

7.4.1 (mandatory) Bare conductors ≥ 3.5 m (2.5 m with IP2X mesh barrier).

7.6.12 Conduit ID ≥ 1.5 × cable OD.

7.6.14 Tray fill: power 40%, control 50%.

7.6.35–7.6.36 Underground: ≤ 6 cables per route; depth ≥ 700 mm (1 m farmland); 100 mm sand bed; protection plates.

7.6.52–7.6.57 MI cables: bending radius 2D–6D; S/Ω loops at thermal expansion and settlement joints.

7.7.5 Electrical shafts: 1-hour fire rating; service doors to corridors; floor sealing.

7.7.6 HV/LV/emergency circuits in one shaft: ≥ 300 mm spacing or barriers.

Practical takeaways

For designers familiar with PUE or IEC 60364, GB 50054-2011 is conceptually close: 30 mA RCDs, TN-C-S, equipotential bonding, selectivity. Key differences: 220/380 V, GB 1002 sockets (flat pins), 1.5 mm² minimum fixed copper, fire RCD 300 mA, PEN must not pass through switching devices (as in PUE 1.7.133).

Design with GorkyCAD Pro

Automatic single-line diagrams, PUE/GOST/IEC calculations, specification and PDF — from one model.

Start free

Data is for reference. Final design decisions must follow current regulations and a qualified engineer.
← Back to the country: China: electrical installation rules (GB 50054, GB 50303, JGJ 16) · World electrical installation rules