Top.Mail.Ru

SP 256.1325800.2016 Electrical installations of buildings (Russia) — translation

The main Russian code of practice SP 256: protection measures, bathroom zones 0–3, 30/10 mA RCDs, sockets, lightning protection. IEC 60364-based.

🇷🇺 PUE — Rules for Electrical Installations (7th ed.)🕰️ PUE-6 — Rules for Electrical Installations (6th ed., 1985)🇺🇸 NEC — National Electrical Code (NFPA 70)🇪🇺 IEC 60364 / HD 60364 (EU national codes)🌎 NOM-001-SEDE, NBR 5410, AEA 90364, RETIE, NCh 4, CNE🇨🇳 GB 50054, GB 50303, JGJ 16, GB/T 16895 (IEC 60364)🇮🇳 IS 732

Document

DocumentSP 256.1325800.2016 Electrical installations of buildings (Russia)
Edition2016
StatusCurrent (SP 256.1325800.2016)
Issued byMinistry of Construction of Russia
Applies toElectrical design of residential and public buildings: protection, bathroom zones, RCDs, lightning

Document structure

№Chapter / section
4General
5Power supply
7LV installations
7.3Protection, RCDs, bonding
7.4Bathrooms: zones 0–3
10Lightning protection
PUE 7, Section 1PUE 7, Section 7PUE 7, Chapter 2PUE 7, Chapter 3PUE 7, Section 1PUE 7, Section 1PUE 7, Section 1PUE 7, Chapter 1PUE 7, Section 6 LightingSP 256PUE 7, Section 1PUE 7, Section 1PUE 7, Chapter 2PUE 7, Chapter 4PUE 7, Chapter 7PUE 7, Chapter 7GOST R 50571 Building electrical installations (Russian IEC 60364)PUE 7, Chapter 2PUE 7, Chapter 7SP 158PUE 7, Chapters 2SP 76GOST R 50571Japan: electrical rules (JIS, 100 V)

Overview

SP 256.1325800.2016 — the main Russian code for building electrical installations, based on IEC 60364 (via GOST R 50571). Used together with PUE.

Section 7. LV installations

7.1 TN-S/TN-C-S for buildings; PEN split at the intake.

7.2 Automatic disconnection, double insulation, SELV; 0.4 s.

7.3 30 mA RCDs for dwelling socket circuits; fire RCD 100–300 mA; bonding.

Bathrooms (7.4)

Zones 0–3 (per IEC 60364-7-701): 0 — bath volume; 1 — to 2.25 m; 2 — 0.6 m around; 3 — 2.4 m around. SELV in zones 0–1; sockets outside zones 0–2 (zone 3 with 30 mA RCD); IPX4/IPX7 luminaires; supplementary bonding.

Sockets

Height 0.3–1.0 m; kitchen ≥ 4 sockets; bathroom sockets on 10–30 mA RCD; all sockets with PE contact.

Design with GorkyCAD Pro

Automatic single-line diagrams, PUE/GOST/IEC calculations, specification and PDF — from one model.

Start free

Data is for reference. Final design decisions must follow current regulations and a qualified engineer.
← Back to the country: PUE Russia: Rules for Electrical Installations · World electrical installation rules